Photo documentation

Click right-hand mouse key to download

The site
July 2001
Download

The site
July 2001
Download

Initial preparations
August 2001
Download

Still a country lane:
EVN Abfallverwertung NÖ Road
Download

EVN Abfallverwertung NÖ Road
July 2001
Download

Start of construction
August 2002
Download

Digging for the bunker
curtain wall
Download

Digging for the bunker
curtain wall
Download

Plant foundations
Download

Earthworks
Download

Site in September 2001
Download

Bunker walls installed
Download

Site in October/November 2001
Download

Start on the stairwells
January 2002
Download

Completion of the stairwells
Download

Bunker excavation and steel works
Download

Boiler scaffolding
Download

Delivery of the boiler walls
Download

Installation of the boiler
Download

Steam pipeline to the Dürnrohr station
Download

Delivery of the SO2 scrubber
Download

SO2 scrubber lifted into the scaffolding
Download

Smokestacks foundations
Download

Raising the smokestack
Download

Raising the smokestack
Download

Installation of steam drum
Download

Waste feeder
Download

Installation of the waste feeder
Download

Completion of the steel structure and control centre
Download

Preparing the tracks for
railway delivery
Download

Entrance view
Download

Completion of the waste bunker
Download

Slag hall and ash silo
Download

Laying the tracks for the
railway siding
Download

Perspective view
July 2002
Download

Carcass of the flue gas
cleaning plant
Download

Construction of the bunker roof
Download

Grate
Download

Works managers meeting
Download

Installing the smokestack top
Download

The two smokestacks
Download

The plant in September 2002
Download

Boiler installation
Download

Laying the tracks for the
railway siding
Download

Completion of the bunker
Download

Garbage feeding hopper
Download

The bunker is completed.
The construction machinery is removed
Download

The bunker is completed.
The construction machinery is removed
Download

The bunker is completed.
The construction machinery is removed
Download

Laying the craneway tracks for
container discharge
Download

Boiler installation
Download

Control centre
Download

Northern view of the plant and reed sewage treatment plant
Download

Railway tracks and container
craneway
Download

Bunker
Download

Installing the flue gas
cleaning system
Download

Flue gas cleaning system
Download

Slag bunker
Download

The plant in November 2002
Download

Boiler lining
Download

Fire pond
Download

The plant in December 2002
Download

Fabric filter
Download

Pressure test successfully completed
Download

January 2003
Dürnrohr power station and EVN Abfallverwertung NÖ plant link operations
Download

January 2003
Dürnrohr power station and EVN Abfallverwertung NÖ plant link operations
Download

March 2003
Garbage delivered by railway
Download

March 2003
Unloading a railway container
Download

March 2003
Download

March 2003
Fire pond at the northern side
Download

March 2003
State-of-the-art container unloading
Download

March 2003
The first garbage supply is delivered
Download

March 2003
First delivery of garbage in the bunker
Download

EVN Abfallverwertung NÖ managers feed the first 20 tons of garbage into the plant
Download

EVN Abfallverwertung NÖ managers feed the first 20 tons of garbage into the plant
Download

The grate is first stoked
Download

The first fire on the grate
Download

The first slag
Download

Almost pure steam.
The first smoke rises
Download

Garbage shipped in special railway containers
Download

First garbage truck passes the gate
Download

Automated unloading of container
Download

Container is emptied into the
garbage bunker
Download

Garbage burning in the boiler – to be monitored through a peephole
Download

First garbage supply is fed to the bunker
Download

First garbage supply in the
EVN Abfallverwertung NÖ bunker
Download

EVN Abfallverwertung NÖ plant in May 2003
Download

Southern view of EVN Abfallverwertung NÖ plant and automated container craneway (August 2003)
Download

View of completed plant, August 2003
Download

EVN Abfallverwertung NÖ plant combined with
the Dürnrohr power station, August 2003
Download

Full operation as of 1 January 2004
Download

Slag bunker and inert slag
Download