Currently, boiler assembly is about to be completed. The flue gas cleaning system is scheduled to be finished in late September. The top part of the SO2 scrubber, newly constructed in Taiwan, was installed in late June. “Cold startup” – which involves checking the controls and instruments and the direction of rotation of the engines, pressure tests, etc. – has already begun. As to the construction works, the entrance hall is shortly to be finished. The outdoor facilities are set to be completed by the end of 2009. Startup with garbage – the first time waste is incinerated on the grate – is planned for the end of November 2009. |