Built-up area: 11,000 square metres |
| > |
Tallest buildings:
3 steel smokestacks of 100 metres each, five staircases of
48 metres each |
| > |
Garbage bunker volume: 40,000 cubic metres |
| > |
Altogether 90,000 tons of reinforced concrete and 6,000
tons of steel girders went into the plant |
| > |
The site offered employment to some 200 to 300 construction
workers per day |
| > |
Operating staff: 75, five shifts of six staff each |
| > |
Cost of total plant: approx. € 270 million |